At the beginning of the decoration, the following steps are roughly followed:
1, plumber
Slotting:
According to the design requirements, dismantle and open all pipe trunking (water supply and drainage roads, strong and weak current lines) and various walls.
Completion time: generally 3 days (if the room type changes greatly, you need to knock on the wall first, and the time may be extended)
Wiring:
Installation and arrangement of circuits, waterways and gas circuits.
Completion time: generally 4 ~ 7 days.
2. Mud (water) bricklayer
Surface decoration of civil engineering and wall and floor tiles:
Landfill trough, wall construction, all kinds of wall repair, floor tile and wall tile laying.
Completion time: generally 10 ~ 25 days.
3. Woodworking
Decoration and accessories production:
All decorative surfaces (walls of heaven and earth) and furniture shall meet the design requirements.
Completion time: generally 15 ~ 30 days.
4. painter
Decorations such as furniture and walls:
All wooden furniture, decorative surface decoration, ceiling and wall painting (latex paint, wallpaper wall covering).
Completion time: generally 20 ~ 40 days, especially when doing wall paint, which has a great relationship with the weather.
5. Electrician
Installation of lamps, etc
Completion time: generally 3 ~ 4 days.
6. Others
Curtain installation, self-purchased hardware pendant installation, and overall land reclamation and cleaning.
Completion time: generally 3 ~ 4 days.
7, need to pay attention to the external completion.
Now you can buy some furniture (such as sofa, dining table, etc. ) and move. It is recommended to stay for half a month or longer. If the materials used are environmentally friendly, there is no need to deal with indoor pollution after renovation, but attention should be paid to opening more windows for ventilation.