Current location - Health Preservation Learning Network - Health preserving recipes - The following is a detailed table of the decoration process.
The following is a detailed table of the decoration process.
My mother didn't arrange the decoration order of rough houses in such detail.

Nanny level decoration flow chart

I. Pre-construction (about 30 days)

The decoration company made it.

1, measuring room 2, drawing design (about 20 days)

What I want to do

1, go through the commencement formalities (go to the property for the commencement permit).

2. Pay the decoration deposit

Ready to buy

1, central air conditioning, floor heating, fresh air, water purifier (choose and pay the deposit before construction, and make an appointment for the door-to-door time of construction)

2, security doors, windows 3, the whole house custom cabinets, wardrobes

Matters needing attention

1, according to living habits, fully communicate the design with designers, and start construction after being satisfied.

2. Make a decoration budget table. The more accurate the budget, the less budget overruns.

3, prepare the material schedule, advocate material should be purchased in advance by stages.

Second, the demolition stage (about 10 days)

The decoration company made it.

1, shovel the wall skin 2, dismantle 3, build a wall 4, seal the balcony 5, clean up the garbage 6, and measure the cabinet about one foot.

What I want to do

1, contact vehicle 2 for removing construction waste, and confirm floor heating and paving methods.

3. Determine the kitchen appliances (you don't need to buy them first, but you need to determine the model and size of embedded household appliances in advance).

Ready to buy

1, temporary toilet, sewer pipe protective cover 2, smoke pipe, check valve (to be embedded during hydropower transformation) 3. Sanitary ware to be embedded: toilet, wall faucet and embedded shower head.

Matters needing attention

1, floor drain protection to prevent construction waste from blocking the sewer.

2. If you want to install a water purifier, water dispenser, garbage disposal, etc. You should get together.

3. If it is necessary to cooperate with the intelligent equipment of the whole house, the preliminary construction shall be carried out in the demolition stage.

4. Plan the layout of the switch socket.

III. Hydropower transformation (about 10 day)

The decoration company made it.

1, water and electricity disclosure 2, slotting 3, water circuit laying 4, wall drainage and water transformation 5, embedded faucet 6, punching 7, toilet backfilling 8, kitchen and bathroom waterproofing 9, central air conditioning and floor heating installation.

What I want to do

1, contact the window merchant and the cabinet merchant, and take measurements at home.

2. Take photos to record the location of water and electricity for later maintenance. 3. Do a good job of acceptance after the completion of hydropower.

Ready to buy

1, indoor door, kitchen sliding door, bathroom door 2, shower room 3, shower room water stop 4, wall brick/floor tile 5, floor drain 6, threshold and windowsill stone

Matters needing attention

1, in the early stage of hydropower, you can buy a floor drain online, which is cheaper.

2. The confirmation of hydropower station requires the presence of the owner, designer and long-term worker. Mark with chalk after completion (take photos to record the position for later construction).

3. After the completion of water and electricity, remember to ask the master for a statistical table of the quantity and size requirements of switches, sockets, spotlights and downlights, so as to facilitate the online shopping of related materials in the later period.

Fourth, the bricklayer stage (about 30 days)

The decoration company made it.

65438+

9, ceramic tile ground protection

What I want to do

After the tiles are pasted, they will be re-measured by the whole house custom merchants, interior door merchants and shower room merchants.

Ready to buy

1, caulking agent, masking paper dust-proof protective film 2, wood floor 3, plastering line 4, aluminum gusset ceiling

5, downlights, spotlights, linear light slots 6, bathroom embedded Yuba, kitchen cool bully

Matters needing attention

1. Closed water test (48 hours). The owner needs to greet the neighbors downstairs in advance and inform the property.

2, ceramic tile acceptance, count the number, dismantle check whether level off; If bricks need to be butted, make it clear.

Five, woodworking stage (about 25 days)

The decoration company made it.

1, woodworking base 2, ceiling of the whole house (curtain groove reserved) 3, abnormity 4, lamp embedment 5, flue pipe embedment 6, lamp opening position, size 7, measuring door 8, installation of range hood, cooker and sink.

9, woodworking acceptance

What I want to do

1, wallpaper (on demand) 2, wall paint (one bottom and two sides) 3, floor protective film

Ready to buy

1, caulking agent, masking paper dust-proof protective film 2, wood floor 3, aluminum gusset ceiling 4, downlight, spotlight, battle light trough.

Matters needing attention

1. Check whether there are no dry cracks in the material. 2. Brush moistureproof paint.

3. Try not to place an order in rainy days. 4. Measuring cabinets, indoor doors and customized products.

Transformation stage of intransitive verbs (about 10 days)

The decoration company made it.

1, wall treatment 2, determination of additional materials 3, grinding acceptance 4, color matching and painting 5, garbage cleaning 6, cabinet size.

What I want to do

Make an appointment in advance to install customized cabinets, interior doors, doorsills, wooden floors and skirting lines in the whole house.