Zhong Da consulted Bian Xiao to sort out the relevant contents and the calculation contents of cantilever retaining wall:
Zhong Da Consulting combed the contents of relevant calculation formulas, mainly including:
Calculation of (1) earth pressure
1. Vehicle load conversion is based on the formula in Table 3-2-6, including
h0 = 200.00/γ[ 13.0+0.577(H+2a)]
= 200.00/( 18*( 13+0.577*(5.5+2*0))
= 0.687m2 Calculate the earth pressure with Rankine formula (β=0).
Ka=0.27 1 σ0=γh0Ka
= 18*0.687*0.27 1
=3.35 1 kPa
σH =γ(h0+H)Ka
= 18.0*(0.687+5.5)*0.27 1
=30. 180 KPa According to formulas (3-6- 1) and (3-6-4), the earth pressure e and the moment arm y of the whole wall are e =1/2γ H2ka (1+2h0/h).
=0.5* 18*5.5*5.5*0.27 1*( 1+2*0.687/5.5)
= 92.2 1 1kn y =(3h 0+H)H/3(2h 0+H)= 2.0 17m
Based on the above information, the main process of cantilever retaining wall construction generally includes:
Measuring and setting out → Foundation pit excavation → Foundation pit treatment and gravel cushion → Foundation reinforcement processing and formwork construction → Setting settlement joints → Foundation concrete pouring and maintenance → First floor wall reinforcement processing and installation and formwork construction → First floor wall concrete pouring and maintenance → Backfilling, drainage holes and filter layer → Second floor wall reinforcement installation and formwork construction → Second floor wall concrete pouring and maintenance → Backfilling drainage holes and filter layer → coping.