Venue: Baodi Building 1 1 Floor Meeting Room
Moderator: Wang Lijuan.
Participants: engineering department, technical department, quality department, cost department, supervision company, cost department and various cost departments on site.
The meeting * * * solved four problems:
First, the target cost calculation:
1, the target cost calculation of the implementation version of the scheme version requires the relevant engineering personnel to provide the planned construction period and sign it for confirmation;
2. The target cost calculation of the executive version needs to be signed by the engineering manager of the branch company for confirmation;
3. When setting the target cost, the personnel of the Engineering and Cost Department participate in the formulation.
Second, the project construction contract:
1. Construction scope, building number, quantity, etc. It should be clearly stipulated in the contract that the labor cost and material cost should be as clear as possible.
2. The total contract price shall be compiled by the engineering and cost personnel. The total contract price shall be determined by the project leader through consultation with the support department.
Third, the problems raised by the supervision company:
1, On May 29th, the supervision company listed the detailed quality construction requirements and asked about the cost.
The problems are summarized together with the supervision problems, and the project director, technical director and professional engineer are organized by the cost director to discuss and determine.
Four, the actual practice is inconsistent with the drawings:
1, by the engineering department, technology department, quality department, supervision company * * * to develop a unified collection of practices, according to the unified practice for on-site construction and accounting.
2, the installation of supporting projects, organize supporting engineering personnel to discuss separately.
The details discussed at the meeting are as follows:
First, the target cost calculation problem:
1, the target cost calculation of the implementation version of the scheme version requires the relevant engineering personnel to provide the planned construction period and sign it for confirmation;
2. The target cost calculation of the executive version needs to be signed by the engineering manager of the branch company for confirmation.
3. At present, the target cost has been set, but the actual cost is not enough. For example, the actual cost of the Dabai project in Taijing Mountain City has increased.
Meeting solution: When setting the target cost of the project, engineers and personnel from the cost department will participate in the formulation.
Second, the project construction contract:
1. construction scope: for example, when Bai Gang stair handrails, yard fences, etc. Jointly constructed by several construction units, and the building number is not specified in the construction contract;
Meeting solution: indicate the scope of construction in the contract, such as building number and quantity, and make clear the labor cost and material cost as far as possible;
2. Total contract price: At present, there are problems that the total contract price is too high, too low or not indicated;
Meeting solution: the project and cost personnel will be assessed by the total contract price, and the total contract price of supporting facilities will be determined by the project leader and supporting departments.
Third, related issues raised by the supervision company
1. Establish a platform to ensure that the construction site practices are consistent with the settlement practices and prevent the construction unit from taking advantage of loopholes.
2. The problem of full daubing and scraping is that the shear wall, awning and floor are full of daubing and scraping.
3. All male * * * parts (buildings) shall be plastered.
4. External insulation practices shall conform to the practices given by the manufacturer.
5, the frame structure leakage is more, whether to add leveling layer to the outer wall.
6, Jinzhou quality control measures, should be given a certain fee.
Meeting solution: The supervision company shall list the details before May 29th, and the cost personnel shall determine whether to pay the fees according to the details.
Four. Inconsistency between actual field practice and drawing practice: (including civil engineering and supporting projects)
(1) civil engineering problems
1, the design requirements are different from the actual construction practices:
Example 1. In masonry, when the length of the wall is more than 5m, the specification requires Rachel between the top of the wall and the beam. However, this practice is generally not adopted in construction, but structural columns are added to the wall. How to calculate the cost?
Meeting solution: calculated according to the design requirements of drawings. If the site construction is different from the drawing practice, the engineering manager will issue a change contact form.
Example 2, Rachel reinforcement of the wall, the drawing design requirement is the length, but the actual construction is not the length, how to calculate the engineering quantity?
Meeting solution: Calculate the engineering quantity according to the drawing design requirements.
Example 3: windowsill coping, the drawing design is the same width as the structural wall, but in actual construction, the windowsill coping width exceeds the wall+external wall benzene board. How to calculate this quantity?
Meeting solution: the technical department defines the node practice.
Example 4: The bathroom is next door. The drawing design is partition wall setting, but in actual construction, the bathroom exterior wall is also set. Is this quantity included?
Meeting solution: The technical department made clear the practice and set up the upper edge around the bathroom. For example, 5, the design requires the wall to be 20 thick 1:3 cement mortar. In actual construction, the surface layer and the base layer are separated, with 1:3 cement mortar for the base layer and 1:2 cement mortar for the surface layer. Quotas are also divided into grass-roots and surface levels. The cost was adjusted according to the design requirements, but the construction unit did not agree, saying that the construction could not be carried out. Meeting resolution: the new drawing is changed from the technical department to: 20 thick cement mortar; The settlement of completed projects shall be carried out according to the quota requirements.
Example 6. The partition wall of stairs is a 60-thick lightweight concrete wall, and the actual construction uses a 60-thick blue brick wall, which involves the problem of nesting. How to operate the cost?
Meeting solution: In case of material change, the project leader will issue a change order and submit it to the cost department within 7 days.
2, the design practice is, the actual construction is not done, how to deal with the cost, give it or not? Example 1. The original design of the SBS waterproof layer on the balcony roof of the police apartment project 1:3 cement mortar 20, which was not done in the actual practice?
Example 2: Dongsheng garden project: the corner and end of the constructional column are set according to the drawing requirements; keep
According to the requirements of the contact list, the frame column should be provided with a window of more than 2. 1 m; The actual construction was not done; Example 3: Longqiwan Project: The ceiling of the equipment (warehouse) floor is provided with 40 thick rock wool insulation board, and the concrete floor is poured at the same time. Rock wool has not been used on site;
Example 4. The plastering of the inner wall of the pipeline well shall be carried out according to the drawings. In the actual construction on site, some plastering is easy to happen in the construction unit, some are not plastered, and some are omitted.
Meeting solution: For the above and similar contents, the project leader will issue a contact sheet. For the settlement of the completed project, the project leader will issue a description of the actual practice on site, and the cost personnel will settle the account according to the description.
3, the design can't meet the construction requirements, whether the contact list issued by the project or design contact list:
For example, in the construction method of sticking bricks on the outer wall of the public security apartment project, the fixing method of galvanized welded wire mesh is plastic anchor bolt, which can not meet the fixing of galvanized welded wire mesh. In fact, the U-shaped 8# galvanized wire anchor is added.
Meeting solution: the project leader will issue a contact sheet for similar situations.
4. Does the wall height include the foundation brick?
For example, in masonry, horizontal coupling beams are set when the wall height exceeds 4m. Does this height include the height of the foundation brick?
Meeting solution: The height of the wall does not include the height of the foundation layer. The height above the ground is the height of the wall.
5. The concrete construction of the steps is inconsistent with the design. The design is concrete, but it is actually a brick step.
Solution: * * Same as developing a unified approach.
(2) Installation engineering problems:
1, temporary power consumption (Xu Changxi):
(1) As-built drawings/pre-drawings are sketches drawn by the construction unit, and the drawings indicate the quantities. Generally, field engineers sign this way: The situation is true, what is its meaning? Confirm the quantity of work or confirm the direction of the pipeline?
(2) The size and practice of the well in the sketch are not available. What is the reference for calculation? For example, cable crossing well1.5 *1.5 *1.5.
(3) How to determine the car freight?
2. Supporting projects:
(1) Earthwork problem: Is the amount of trench excavation calculated according to the as-built drawing or the actual construction situation on site? The quota stipulates that the slope should be put when the trench excavation exceeds a certain depth. In actual construction, sometimes the slope is not inclined. How to settle the earthwork at this time?
(2) Soil type
(3) the practice of drainage wells, water supply wells and valve wells?
(4) Buffering method
3. Electrical part of the main building:
(1) Lightning protection grounding part: down lead, test point and grounding grid are often inconsistent with the drawings.
(2) Cabinet wiring: indoor distribution box and power bureau are supplied, and some construction units need cabinet wiring. How to calculate the cabinet wiring part?
(3) Division of fire protection wiring: the fire protection boundary is unclear and too general, and some things are not known whether the fire protection company or the general contractor did it. Are lamps (fluorescent lamps) installed in the distribution room?
(4) Is there any provision for returning the lighting and sockets in the basement?
(5) The drawings are inconsistent with the actual construction, such as the models of wires, cables and pipes used in the drawings, but the models reflected in the financial accounts in the actual construction process are inconsistent with the drawings, and there is no engineering contact list.
4, the main building plumbing part:
(1) In the drawing design, the indoor heating branch pipe bypasses the shear wall and passes through the plastic sleeve brick wall; In actual construction, the indoor heating branch pipe directly passes through the shear wall and adopts steel casing. How to determine?
(2) Water supply and drainage shall be installed according to the drawings. What is the reserved length of the water supply pipe and drainage pipe actually constructed in the kitchen and bathroom? (The upper reflux riser of the drainage branch pipe is reserved 300mm from the ground. In actual construction, each site is different, and the reserved height of toilet and washbasin is also different. How to determine? )
(3) In the drawing design, sometimes the wall bushing or door bushing is not clearly marked. In actual construction, it is necessary to set casing. How to determine?
5, the main building fire part:
Fire electricity:
(1) The function of the wire in the fire alarm system does not conform to the drawing. (Cost reduction) The signal line marked on the diagram is NH-RVS2* 1.0,
In actual construction, the signal line was changed to ZR-RVS2* 1.0.
(2) The wire diameter drawings in the fire alarm system are inconsistent. (According to the acceptance specifications and wiring standards of Gulf manufacturers)
Lighting control line, ZR-BV2* 1.5 on the drawing,
In actual construction, the lighting control line is ZR-BV2*2.5, and the line diameter is increased.
(3) Fire alarm system, the pipeline threading method in construction is inconsistent with that in the drawing.
Some lines in the picture need to be underlined, but they are not marked.
Lines not marked in actual construction shall be laid according to the acceptance specifications.
Fire water:
(1) Indoor and outdoor boundary between fire hydrant and spray pipe. There is no flange at the building skin 1.5m, but there are 1 flange in actual construction.
(2) Outdoor fire water pump adapter, butterfly valve+new water pump adapter. There is no butterfly valve in the drawing, but there is one in actual construction.
(3) Brush oil on the supports and hangers. Drawings show that the bracket is brushed with antirust paint twice after rust removal, and gray ready mixed paint twice. In actual construction, the bracket shall be brushed with antirust paint twice after rust removal.
Meeting solution: Support engineers discuss the installation of support projects.
Minutes of Exchange Seminar [Chapter II]
On the afternoon of August 20 15, Li Xin, the general manager of the company, presided over a special exchange meeting to solve the adaptability problems of students during their study in Tengpu Science and Technology. Dean Li Xingtai, heads of relevant departments and students of 1 class attended the exchange meeting. The summary is as follows:
I. Answers to related questions.
1, learning without confidence.
Students should be clear that the purpose of studying in Tengpu is to improve their abilities in an all-round way, so as to become an entry-level qualified labor force, have a satisfactory job after graduation, live a happier life and strive for a happy life on their own. Everyone can realize their own shortcomings and bravely walk into Tengpu, so we must be confident that we can become the top talents in the industry. Even after six months of inhuman training, they will never give up. Believe in yourself and stick to it until you see the rainbow after the storm.
2. The problem of poor computer foundation.
In view of this kind of problem, Dean Li suggested that we classify the related problems: basic computer operation problems can be solved by searching relevant information on the Internet or consulting classmates. If conditions permit, the teaching and research section will transfer experienced computer basic teachers to do basic training for everyone; Professional software operation problems should be consulted with relevant professional teachers, and problems should be solved in time when found.
3. Insufficient time allocation and poor learning efficiency.
Insufficient time allocation and poor learning efficiency are due to students' failure to reasonably allocate target time nodes, clearly analyze their basic ability level and rationally use resources, which leads to blindness.
Objective To learn by reading. Without a scientific and reasonable learning method, I am busy all day but feel mediocre. Students should be good at active learning, actively absorb scientific and cultural knowledge and life-related skills, integrate interests and goals, take the initiative to learn and be good at learning.
4. The problem of failing the exam
The two exams this week were basically unsatisfactory, which led to a blow to many students' learning confidence. This kind of problem is a problem that many students will encounter after studying the exam. First of all, they should have a correct attitude towards exams and use them as a tool to test their academic performance. Secondly, they should be good at analyzing the reasons for failure in the exam and turn the discouragement of failure into motivation for learning.
5. The basic accounting questions are too difficult.
This exam is very difficult. The teaching and research team will analyze the relevant papers and form an analysis report to support the data. Relevant students should also have a correct attitude, be good at drawing inferences from the teacher's basic knowledge, actively explore the extension of basic knowledge, develop the habit of active learning, and reach a higher level, instead of just staying in the basic learning part.
II. Speech by President Li
This meeting is mainly to solve the problems that students have recently encountered in their studies. I hope that students can keep in mind the "three ones" concept of "one mouth, one pen, one pair", think more, do more things and express more, study hard related professional knowledge, correct learning attitude, establish self-confidence in learning, demand themselves with the standard of "six thinking hats", allocate time reasonably, allocate learning target nodes, and establish self-learning-centered growth.
In learning, we should change the thinking of traditional university exam-oriented education, actively learn scientific and cultural knowledge, be good at finding problems in learning and solving them by using the resources we can control, change passive learning into active learning, demand ourselves with target nodes, test ourselves with relevant exams, and arm ourselves with good mentality, strong interest in learning, strong thirst for knowledge and great belief in achieving goals.
Change learning methods, control personality problems and personality problems reasonably, talk about problems encountered in learning, be good at solving and summing up experience, and form your own unique learning methods to improve your personal ability in an all-round way. The future society is a society with accumulated knowledge and experience. Only those who are good at summing up, analyzing and absorbing experience and doing basic skills under the iceberg can be comfortable in future study.
Success is tempered by wind and rain, and opportunities will only be reserved for those who are prepared. I believe that the half-year training in Tengpu will definitely lay a solid foundation for a better life in the future.
Third, supervision matters.
1. In view of the poor computer foundation of students, please ask the teaching and research group to allocate teaching resources reasonably, and arrange a teacher with rich experience in computer basic operation to do appropriate training for the computer basic part when conditions permit; This basic accounting exam is not ideal. Please ask the teaching and research group to analyze the reasons for the failure of the exam, form a written report, and make up the accounting foundation. In the teaching process, we should change the teaching mode, be good at integrating pre-knowledge and post-knowledge, and allocate teaching knowledge reasonably according to students' learning and understanding ability.
2. The talent service department, the comprehensive department and the teaching and research section explore the establishment of a student-centered growth education system, and make corresponding solutions to the problems that may arise at various stages of students.
3. In view of the five questions raised by the previous students, please put forward your own solutions and make your own learning project management plan according to the requirements of the learning target node and the "six thinking hats", and submit the electronic version to the class teacher before September 1.
Participants: Li Taiyuan (Dean), Li Xin (General Manager), Sang Dayong (Chief Expert of Teaching and Research Section), Cao Yu (Director of Human Resources Department), Chen Yuqing, Hou Pei, Tan Yi, Miao Xiaoxiao, Wang Zixi, Xie Huan and Zhu Bao.
Minutes of meeting: Yue
August 20 15 17
Tengpu technology
Submitted: General Manager's Office, General Department, Teaching and Research Section.
Minutes of Exchange Seminar [Chapter III]
I. Meeting time: 20 15 17 10/October 65438.
Two. Venue: Hotel
Participants: Wu Youming, Zhang, Li Jing, Chen Gang, Hou Shaonan, Liu Fang,.
Li feng Chen Mao jun
Four. Moderator: Wu Youming
Verb (abbreviation for verb) Minute of meeting:
Content of intransitive verbs meeting:
(1) Wu Youming 20 15 Summarizes and analyzes the development status of the media industry. The trend of capital market in media industry is relatively mild. The fundamental reason is that after the strong rise of 20 15, 20 15 entered the stage of logic test and digestion and valuation, and the market sentiment cooled down. But a new model is gradually taking shape:
(B) Media development under the macro-policy environment. The upper level has issued many policies to promote the development of cultural industries and support the integration and transformation of state-owned enterprises. State-owned media enterprises have ushered in an opportunity to take off, and substantive cases have also appeared intensively.
The great influence of the internet. Internet giants have laid out cultural and entertainment industries in depth, and the integration trend of traffic and content in the new media era has begun to appear;
(D) The appearance of M&A tide. M&A has the characteristics of cross-border transformation, which is essentially driven by the needs of enterprise transformation and the interests of both parties. At the same time, the IPO opened, which led to the merger of 20 15.
The purchase logic gradually disappears, and the capital platform will return to the standard when it has money.
(5) The key resources affecting the development of the industry are reflected in two aspects: First, as a special industry with propaganda function, the influence of the upper will and policies is beyond doubt. It is manifested in two dimensions: 1. Policy support will be beneficial to industrial development, and direct economic support such as tax incentives and financial subsidies and soft support such as promoting system reform will substantially help enterprises; 2. State-owned media groups have inherent advantages in policies and licenses, and have benefited the most from the policy-driven industrial evolution.
limited company
20 15 years 1 month 17 days