1, pier (abutment) has been completed;
2. The fabrication of simply supported beam has been completed.
Second, implementation
1, placing temporary supports on piers (platforms) (sandbox method is often used);
2. Hoist the simply supported beam and put the simply supported beam on the temporary support;
3. Hoist the simply supported beams of adjacent spans and place them on temporary supports;
4, above the pier, at the intersection of two simply supported beams, connect steel bars, erect formwork, pour wet joints, maintain health, and apply prestress;
5, after the completion of health, demolition, placement of permanent bearings, temporary bearings, can be completed.
6. Dismantle temporary supports and beams