Current location - Health Preservation Learning Network - Fitness coach - Which line of Wuhan subway goes to Huangpi Qianchuan? What time does it open?
Which line of Wuhan subway goes to Huangpi Qianchuan? What time does it open?
It is the northern extension of Wuhan Line 7 and the third phase of Line 7. Now the first phase of Line 7 is still under construction and will be opened to traffic at the end of 20 17. The second phase has not been decided, let alone the third. This is an active nine-year plan, which is expected to be completed around 2025!

I. Overview of Network Planning

The total length of Yuan Jing rail transit network is 1 100km, with 594 stations and 25 lines, of which the loop line is 60km long. Among them, the internal network scale of the main city is 533km, with 365 stations. This plan was approved by Wuhan Municipal People's Government on April 20 15 (No.41No.of Wu Zhengban [20/KLOC-0]).

Second, the general situation of construction planning

Wuhan Urban Rail Transit Phase IV (20 17 ~ 2025) includes lines 12 (loop),1(Phase III), gedian section, 19, 16 and Qianchuan line. Line 8 (Phase III), 13, Line 7 (Phase III), Jinkou Line and Line 20 are 14, which is about 423.5km long. The general situation of each line is as follows:

Line (1) 12 is planned as a loop, with a total length of about 60.4km and 35 stations.

(2) The third phase of the line 1 1 starts from Sino-French Eco-city Station in Hanyang, and connects with the east section of the second phase of the line 1 1, with a length of 28.2km and a station of1. 1 1 The gedian section of the line extends eastward from the Zuo Ling section of the second phase terminal of 1 1 to Gedian South Station, with a total length of 3.3km and a station of 1.

(3) The19 line starts from Heping Park and ends at Guanggu Free Trade Zone in the south, with a total length of 29.8km, with 1 1 station.

(4) Line16 belongs to the suburban line, starting from Hannan Avenue in Hannan District in the south and ending at Guo Bo Central Station of Line 6 in the north, with a total length of 34.3km and 3 stations 13.

(5) Qianchuan Line starts from Zhifu Road in Qianchuan and ends at Maji Road at the entrance of Wuhan University of Light Industry (gold and silver lake Campus), with a total length of 34.3km and 8 stations (excluding Maji Road Station).

(6) The starting point of the third phase of Line 7 is located in the planned T4 terminal of Tianhe Airport, and the ending point is connected with the Qianchuan Line of Longteng Avenue. The total length of the line is about 6.6km, with 2 stations.

(7) The second phase of Line 6 starts from gold and silver lake Park Station, the end of the first phase of the project, and ends at Zoumaling Station along Jinshan Avenue. The total length of the line is about 15. 1km, with 9 stations.

(8) Line 21Phase II (Yangluo Line) starts from the National Fitness Center Station between Tazihu West Road and Tazihu East Road and ends at Houhu Avenue Station of Yangluo Line Phase I, with a total length of about 3.2km and two stations.

(9) The10 line starts from Changfu and ends at Shigang Station, with a total length of 87.6km and 37 stations.

The (10) 14 line starts from Zhuyehai South Station and ends at Dijiao Depot. The terminal station is located on the south side of the depot, with a total length of 27.2km and 2 1 station.

(11) The third phase of Line 8 is connected with the second phase of Line 8, starting from Yezhi Lake and ending at Huangjia Lake, with a total length of 3.7km and two stations.

(12) 13 line starts from Gutian area and ends at Nanhu Avenue Station, with a total length of 40.4km and 27 stations.

(13) Jinkou Line starts from Lingwu Village Station on the ring road and extends southward along Qinglinghe Road to Jinkou General Motors Base. The total length of the line is about 20.3km, with 8 stations.

(14) Line 20 starts from Wuhan Station and ends at Tianhe Airport, with a total length of about 30.3km and 6 stations.