House decoration process sequence table, decoration has become a major event for many families. When decorating a house, it is a headache for people who have no decoration experience. Next, I will bring you the sequence table of house decoration process.
House decoration process sequence table 1 1, house installation steps-preliminary design
The contents of design before decoration include: 1, defining the area involved in decoration; 2. Determine the wall size.
2, the steps of the house-the main demolition.
The demolition and transformation of the main body is the first step of decoration construction, and its main projects include: shoveling wall skin, replacing plastic steel windows, tearing down walls, building walls, etc.
3, housing installation steps-hydropower transformation
Hydropower transformation is the most noteworthy link in the whole decoration process, so the owner should control every detail of hydropower transformation.
4, the steps of installing a house-carpentry, bricklayer, oiler
Woodworking, bricklayer and oiler are the "three brothers" of construction, and the correct order is: woodworking, bricklayer and oiler.
5, house installation steps-bricklaying
Because the technology of bricklaying is very important, it is generally necessary to invite a master with more than ten years of experience to complete this link, otherwise it will cause a series of troubles. 6, house steps-painting the walls
Painting the wall mainly refers to completing the basic treatment of the wall, painting the wall and painting the furniture.
7. House steps-kitchen ceiling
The ceiling of kitchen and bathroom and the ceiling of cabinet directly determine the aesthetic degree of house decoration, so the owner must strive for perfection in its brand selection.
8, house steps-cabinet installation
Under normal circumstances, the installation of cabinets can be completed within one day.
9, house steps-wooden door installation
When installing wooden doors, lock, floor suction and hinge should be installed, so the owner must prepare relevant hardware accessories in advance.
10, house installation steps-floor installation
In general, the floor installation project can be completed in one day.
1 1, house installation steps-wallpaper paving
If conditions permit, you can do some maintenance on the floor while laying wallpaper, and try your best to "have nothing" on the wall.
12, house installation steps-radiator installation
Radiator is essential for every family, but it should be noted that radiator can only be installed after wallpaper is pasted.
13, house installation steps-switch socket installation
The installation of switch socket is a link that the owner needs to pay attention to. Generally, it is enough to decide the installation position of the switch socket according to your own needs.
14, house installation steps-lamps installation
After the lamps are installed, the feeling of home comes out.
15, house installation steps-hardware and sanitary ware installation
After the installation of hardware and sanitary ware, the owner will feel a sense of accomplishment.
16, house installation steps-curtain rod installation
The installation of curtain rods means the basic end of home improvement.
17, steps of installing the house-furniture entering the site
Owners must know the size range of furniture, otherwise there will be a lot of trouble.
18, house installation steps-home appliances enter the site
The house decoration is completed after the home appliances enter the site.
House Decoration Process Sequence Table 2 (I) Pre-design
The same is construction. The difference between people and bees is that the construction of bees is a reflection of instinct, and before construction, people will form ideas and frameworks in their minds. Therefore, if we compare home improvement to a battle, then the preliminary design of home improvement is the "battle plan" of this battle and the "soul bond" of home improvement. ? In the preliminary design, one thing that must be done is to measure the room in detail, mainly including:
1. Define the areas involved in the renovation process. Especially tile area, wall paint area, wallpaper area and floor area;
2, clear the bearing wall size. Especially it is necessary to design the wall size of furniture in the future. ? In addition, we should be careful not to forget to go to the property to go through the formalities of starting construction, and pay the decoration deposit before starting construction.
(two) the main body is removed or changed.
When entering the construction stage, the main body removal is the first project, which mainly includes wall removal, wall building, wall skin removal, heating removal, plastic steel window replacement and so on. To put it bluntly, the main body demolition is to put up the framework of the construction site first.
(3) Hydropower transformation
Before the water circuit reform, the main structure should be basically completed. Between the hydropower transformation and the main body demolition, the first test of the cabinet should also be carried out. The so-called initial measurement of cabinets has no actual content, because the walls and floors have not been treated, and it is impossible for cabinet designers to give specific design dimensions, but only put forward some relevant suggestions on the positions of water inlets and lampblack machine sockets reserved by developers. Mainly includes:
1, to see whether the position of the lampblack machine socket affects the installation of lampblack machine in the future;
2. See if the location of the water meter is appropriate;
3. See if the location of the water inlet is convenient for installing the sink in the future. ? The cabinet is measured for the first time. Those who have a little experience can do it themselves. After the waterway reconstruction is completed, it is best to waterproof the bathroom immediately. The kitchen generally doesn't need to be waterproof.
Unless it is the main material needed for the demolition of the main body, the entry time of main materials such as tiles and large core boards should be after the hydropower transformation. Because if the circuit transformation involves slotting on the ground, if the tiles and core boards are not properly placed, it will be very troublesome for workers to walk around.
(4) Woodworking
Woodworking, bricklayer and oiler are the "three brothers" in the construction process, and the basic order of appearance is: wood-tile-oil. The basic entry principle is-whoever is dirty goes first. "Who gets dirty first" is also one of the basic principles to determine the order of home improvement. ? In fact, carpentry, such as vertical pipe, decorative ceiling and plaster line, can also be considered as the fine link of main demolition and reconstruction in a sense, which does not conflict with the water circuit reconstruction itself, and sometimes needs some cooperation. If you are going to make a fake wall at home, you should consider whether there are water and electricity lines on the fake wall. If there are, let the water and electricity reconstruction workers embed the pipes.
(5) Tiling
If the workers are busy, the foreman will usually ask the "second bricklayer" to stick bricks in the field before the "carpenter boss" finishes. This is normal, because the two do not conflict. ? During the operation of "bricklayer's second child", the installation of the following three links is also involved:
1. Installation of lintels and marble windowsills. The installation of the threshold can be completed together with the floor tile laying, or after the floor tile laying. Generally, after the window cover is completed, the marble installation union prepares glass glue and seals the marble and window cover with glass glue.
2. Install the floor drain. Floor drain is the first hardware in home decoration, because it should be installed with floor tiles. Therefore, when you start to buy building materials, you should buy a floor drain as soon as possible.
3. Installation of range hood. The range hood is the first appearance of household appliances. After the kitchen walls and tiles are paved, you can consider installing a range hood. ? When the "second bricklayer" left the scene, it was time to measure the cupboard for the second time. Accurately speaking, after the kitchen wall tiles are pasted and the range hood is installed, it is time to measure the cabinet for the second time.
(6) Paint the wall
The "Third Oil Worker" enters the site, mainly completing the basic treatment of the wall surface, painting the top coat and brushing the furniture made by the "carpenter". Students who are ready to paste wallpaper only need to let the "third oil worker" do basic treatment on the wall surface where wallpaper is planned. As for whether I left my coat for the last time, I personally don't think it is necessary to take this question too seriously. From my experience in decoration, it is of little significance to leave the top coat, because the operation behind is not dirtier than painting.
(7) Ceiling of kitchen and bathroom
As an installation link, the cabinet ceiling is still continuing the "packaging" of the home. At the same time as the ceiling of the kitchen and bathroom, the moisture-proof ceiling lamp and exhaust fan (Yuba) of the kitchen and bathroom should have been bought. It is best for the owner to install the kitchen ceiling lamp and exhaust fan at the same time, or leave a line and an opening. Jiuzheng Home reminds that the owner should adhere to the "decoration outsourcing theory", even if the foreman promises how to standardize the water and electricity decoration of workers, how to standardize the installation of aluminum gusset plates, how to make wooden doors, how to make them firm, how to professionally paste wallpaper, and how to make cabinets practical ... In fact, what the decoration team can do is carpentry, tiling and painting.
(8) Install the kitchen cabinet
After the ceiling is completed, you can make an appointment to install the cabinet at home. If it goes well, it can be finished in one day. At the same time, there are sinks (excluding water fittings) and gas stoves. It is best to coordinate the property to turn on the gas before the cabinet is installed, because the gas stove needs to be tested after installation. ? Speaking of the ceiling, there is a problem worth discussing. Many kitchen and bathroom ceilings are made of waterproof gypsum board and coated with waterproof paint. The quotation of decoration team is generally above 120 yuan per square meter, which is more expensive than ordinary aluminum gusset plate and PVC gusset plate ceiling. The gypsum board ceiling looks flat visually, but once there is a problem with the top water pipe in the future, or the upstairs water leaks and needs to be repaired downstairs, the gypsum board ceiling will be removed as a whole, which is much more troublesome than the gusset ceiling. Therefore, everyone should be careful when choosing gypsum board ceiling.
(9) Wooden door installation
The second day after the cabinet was installed, as early as more than a month ago, after the wooden door was measured, it can be installed now. If it goes well, it will be a day. At the same time, hinges, door locks and floor drains should be installed. Related hardware should be prepared in advance. ? If you want the wooden door manufacturer to install the window cover and pass it, you should also measure it when the wooden door manufacturer measures it, and install it at the same time on the day when the wooden door is installed. At the same time, you should consider setting the marble windowsill backward after the window cover is installed. Jiuzheng Home reminds owners that the production cycle of wooden doors is generally one month. Therefore, in order to make the construction period closely connected, it is necessary to let the wooden door manufacturer come to measure the size of the door opening as soon as possible after the main body is removed. Regarding the treatment of the doorway, it should be noted that if the height of the doorway at home is inconsistent, workers need to treat it at the same height-beautiful.
(10) Floor installation
The floor can be installed the day after the wooden door is installed. If all goes well, it will take a day. The floor installation needs to pay attention to the following issues:
1. Before the floor is installed, it's best to let the manufacturer visit to inspect whether the floor needs leveling or partial leveling. Some decoration companies or decoration teams will suggest ground leveling or partial leveling, which shall be subject to the actual investigation of the floor manufacturer;
2. Before the floor is installed, the floor paved at home should be cleaned to ensure the floor is dry, so do not use water during the cleaning process.
3. When installing the floor, if possible, the floor must be cut in the corridor. Some people think it is immoral to cut the floor in the corridor to pollute public areas. Actually, it doesn't matter to clean up after the completion. Cutting the floor indoors has serious pollution to the wall, and cutting the artificial stone countertops of cabinets.
(1 1) Laying wallpaper
The next day after the floor is installed, the home is ready, and you can make an appointment to paste wallpaper. If it goes well, the same day will do. If possible, the floor should be protected on the day of wallpaper pasting; It doesn't matter if there are no conditions, and it's no problem to leave the wallpaper glue left on the floor to Pioneer for cleaning. Before pasting the wallpaper, try to make the wall "nothing".
(12) Installation of radiator
The day after the wallpaper is laid, the person who replaces or removes the radiator can hang the radiator on the wall in a down-to-earth manner. It's also a day. ? Wooden door-floor-wallpaper-radiator, which is recognized as the correct installation sequence. Install the wooden door first to ensure that the skirting line of the floor can be closely connected with the door cover of the wooden door; After the wallpaper was installed, it was mainly because the floor was dirty and dusty, which seriously polluted the wallpaper. Here, the principle of "whoever is dirty first" mentioned above is used again. Finally, install the radiator, because the radiator can only be installed after the wallpaper is laid on the wall.
(13) switch socket installation
We should have a detailed understanding or record of the number and location of switch sockets in various natural rooms at home, especially wallpaper pasting workers. Sometimes the wallpaper worker is irresponsible, and the wallpaper is laid at once, and there is no need for wallpaper knife to mark the position of your switch socket. So, you still need to know what you are doing.
(14) Installation of lamps and lanterns
Install the lights. There is nothing to say. After the lights were installed, the house lit up, saying goodbye to the dazzling light of 100 watt incandescent bulbs during decoration-it felt really good.
(15) Installation of Hardware Sanitary Ware
Before buying pipe fittings, bathroom fittings, toilets, clothes hangers, etc. , are all installed. ? After the "big things" in front are installed, the home is still very "cold". When the lamps and hardware sanitary ware are installed, the home will be "alive", really "alive". It is no exaggeration to say that it will be beautiful to open the dragon water for the first time and watch the water flow out. Convenient, the newly installed toilet at home for the first time will have a great sense of accomplishment.
(16) Installation of curtain rod
The installation of curtain rod marks the basic end of home improvement.
(17) development and cleaning
Don't install curtains before cleaning. When cleaning, don't have furniture and unnecessary household appliances at home, leave as many "planes" as possible, so that the cleaning can be thorough.
(18) Furniture comes into play
As for the purchase time of furniture, it should be after the completion of water circuit decoration at the earliest, so that the basic size range of furniture can be roughly selected.
(19) Home appliances enter the site
At this time, it's time for home appliances to enter the market. It's time to install and prepare to move in!
(20) Home accessories
Home decoration, the last step of home improvement, has changed from decoration to decoration, including the installation of curtains. As for buying curtains, it is best to book furniture first to avoid style conflict. Home accessories also include buying some green plants, hanging murals, decorating handicrafts and so on.
The sequence of house decoration process is shown in Table 3 i. Details are as follows:
1 Go through the commencement formalities -2. Self-measurement -3. Preliminary design -4. Demolition and renovation of the main body -5. Door-to-door measurement of wooden door manufacturers -6. Preliminary measurement of cabinets -7. Hydropower renovation -8. Waterproofing of toilets -9. The main materials enter the site-10 carpentry-10/tiling (. Floor drain)-12 shower partition gauge-13 secondary measuring cabinet-14 wall painting-15 kitchen and bathroom ceiling-16 gas supply-17 cabinet installation (wash basin and gas stove are installed at the same time)-/
Second, the four-step division of the whole process of decoration
Generally speaking, according to the 19 link mentioned at the beginning of the article, the whole decoration process can be roughly divided into the following four links:
1, design the link;
2. Construction link;
3. Install the link;
4, the closing link.
Third, the six-step division of the whole process of decoration
According to the characteristics of the project and the 29 links just mentioned, the whole decoration process can also be divided into the following six steps:
The first step: design ideas;
The second step: the main body is dismantled and changed;
Step 3: Concealed engineering;
Step 4: Cover the project;
Step 5: Installation stage;
Step 6: The closing stage.
Specific instructions:
1, design ideas, in order to be different from bees, we must first have design ideas;
2. The main demolition is to completely turn the blank house into a construction site. The main body demolition and transformation includes the contents just mentioned-"wall demolition, wall building, wall covering, heating removal, plastic steel window replacement, etc." , and some carpentry;
3. Concealed engineering is equivalent to "internal surgery". Do the concealed work first, which is what everyone often says, "renovation begins, water and electricity go first";
4. Covering the project is like "dressing up" the home. Carpenter's window cover, pass, bricklayer's bricklaying, threshold installation and painter's painting-wood, tile and oil-are all basic projects, and clothes will be made after gusset ceiling, floor paving and wallpaper pasting are completed.
5. In the installation stage, the function is mainly realized. Including: cabinets, wooden doors, switch sockets, lamp installation, hardware, sanitary ware, curtain rods ... each has its established functions;
6. In the final stage, to put it bluntly, it is to supplement the factors that do not constitute "immigration".
Third, the popularization of small knowledge-the purchase order of semi-packaged main materials:
1. Cabinets can be ordered in advance or three to five days before the construction party enters the site, because the water and electricity diagram of cabinets is made by the cabinet manufacturer (it takes about one month to customize the products), and the designer delivers the water and electricity diagram to the owner, so as not to delay the trunking.
2. Sanitary ware can be ordered in advance, or three to five days before the contractor enters the site, because the plumber needs to clean up the site when he enters the site, and the drainage should be changed first to determine the size positioning of sanitary ware.
3. Wooden doors can be set in advance or ordered three to five days before the construction party enters the site. This is the long or short distribution of the main materials. Short manufacturers may be able to deliver goods in half a month, and long ones have almost passed more than half of the decoration period. But also a fatal link to delay that work deadline.
4. Walls and floor tiles can be ordered in advance or three to five days before the contractor enters the site. General plastering trade unions will be stationed 10 days after the commencement of construction. At this time, you need walls and tiles to enter the site.
5. Range hood cookware Range hood cookware should generally be considered when setting up cabinets. The slot position of the cabinet table needs the size of the range hood cookware.
6, water heater water heater can be booked early or when sticking bricks.
7. After the clay figurine enters the site, it will be placed for three to five days.
8. Hardware is ordered according to the quantity and time provided by the carpenter. Generally, the construction party will notify the owner three to five days in advance.
9. Wallpapers can be ordered in advance, or three to five days before the top coat construction.
10, the ceiling can be set early or in the middle of the project, because the ceiling is mostly installed by merchants, and it is a project after the wall tiles are laid.
1 1. Lamps can be ordered in advance or in the middle of the project.
12, the floor is basically the last link. Only when the foundation is poorly installed can the floor be installed. It is almost enough to place an order before the middle of the project. If you install solid wood flooring, you need to order it in advance, because you have to play the ground cage.