Polyurethane grouting technology to solve basement leakage?
Polyurethane chemical grouting technology is to inject water-soluble polyurethane chemical grouting material into concrete cracks by using high-pressure power of machinery. When the slurry meets the moisture in the concrete cracks, it will quickly disperse, emulsify, shrink and consolidate, and then the consolidated elastomer will fill all the concrete cracks and completely block the water flow outside the concrete structure, thus achieving the effect of plugging and waterproofing in the basement. Polyurethane chemical grouting base sealing technology is an internationally advanced new waterproof technology of high-pressure airless grouting, and it is also a new technology adopted by water-soluble grouting materials in China at present.

Water-soluble polyurethane chemical grouting material is a low-viscosity, one-component synthetic polymer polyurethane material, which is prepared in advance from excessive polyisocyanate and polyhydroxy compounds and contains free isocyanate groups. It is in the form of mud. When it is injected into concrete crack structure by high pressure, it will cross-link when it meets water, releasing a large amount of carbon dioxide gas and generating secondary seepage pressure. High-pressure thrust and secondary seepage pressure push the elastomer into and fill all cracks, thus achieving the purpose of plugging. Polyurethane chemical grouting substrate has the advantages of simple operation, environmental protection, low cost and good plugging effect.

Water-soluble polyurethane basement plugging agent is made of water-resistant polyether, polyisocyanate, foaming agent and other materials. Because it is liquid before it is formed, it can be widely used in any shape of leakage parts such as construction joints, expansion joints and basement cracks. After pouring into the parts of the basement that need to be sealed, the basement sealing work can be effectively completed within tens of seconds, and the formed data can be firmly bonded with the cracked wall to achieve the purpose of sealing the basement for a long time.

Key points of construction

1, process

Confirm the leakage position → clean the leakage base surface → drill hole → clean → install the water stop needle → high pressure grouting → check → repair the leakage → dismantle the grouting nozzle → repair the groove → check → complete the leakage.

2. Key points of operation

① Cleaning: carefully check and analyze the leakage, determine the location and spacing of grouting holes, clean the area that needs to be cleaned, chisel off the sediment on the concrete surface, and ensure that the surface is clean and moist.

② Drilling: Stop drilling along both sides of the crack with an electric drill. The diameter of the drill bit is 14mm, the drilling angle should be ≤ 45, and the drilling depth should be ≤ 2/3 of the structural thickness. Boreholes must pass through cracks, but not through concrete structures. The drilling spacing is 20 cm -60 cm.

③ Installation of water stop needle: Install the water stop needle in the drilling hole and tighten it with a special Allen wrench, so that there is no gap or water leakage between its periphery and the drilling hole.

④ Seam cleaning: inject clean water with a pressure of 6Mpa into the grouting nozzle with a high-pressure cleaning machine, check the water outlet and clean the dust in the seam.

⑤ Sealing: When the joints are flushed with the base sealing agent, stop sealing the cracks with water seepage to avoid slurry leakage during grouting.

⑥ Grouting: The vertical grouting sequence is from bottom to top, the plane can start from one end, and the single hole can be continuously stopped one by one. When grouting is started in adjacent holes, keep pressurizing for 3~5 minutes, and then stop grouting in this hole.

⑦ Remove the nozzle: After grouting, the exposed grouting nozzle can be removed or knocked off after it is confirmed that there is no leakage. Clean up and clean the solidified spilled grouting liquid.

⑧ Sealing: Stop the repair and sealing treatment of the grouting mouth with the base plugging agent.

Pet-name ruby Waterproofing: Apply three times of chemical grouting (bottom coating, middle coating and top coating) locally with polyurethane waterproof data for external waterproofing treatment.

3. Matters needing attention in construction

3. During leakage grouting at1point, less grouting should be done first, and then more grouting should be done; Vertical cracks, construction joints from bottom to top in turn grouting; Degree or inclined crack grouting from small end to large end; Surface leakage should be grouted from the periphery to the center in turn.

3.2 When grouting, the grouting pipe should be buried reasonably, and the pressure should be closely watched to prevent explosion; Operators should wear glasses, masks, gloves and other labor protection articles.

3.3 Chemical grouting data shall be sealed and kept in a cool warehouse and kept by special personnel. Fireworks are strictly prohibited in the chemical grouting material storage center.

4. Analysis of economic and social benefits

In the leakage stoppage construction of F4# residential building roof basement in Qinhuangdao Oriental Pearl Zone F, the traditional waterproof basement leakage stoppage method was replaced by polyurethane chemical grouting basement, which not only ensured the construction quality, improved the construction speed, but also greatly saved the construction cost and resources. See Table 2 for details:

5. Closing words

Polyurethane chemical grouting waterproof basement plugging technology, as a new type of basement plugging construction technology, has been widely used in cracks, expansion joints and construction joints of various buildings and open-air concrete projects, as well as basement plugging in structural cracks, which not only improves the engineering quality and reduces the labor intensity, but also obtains greater economic benefits in engineering theory, accelerates the development of enterprises, and makes us deeply realize that scientific and technological innovation is the first life productivity.