What is the decoration procedure of blank house?
(a) tools in place, ready.

Before decorating, you must prepare a few things and put them in your bag. Tape measure (buy 5m, not 3m), calculator, big board clamp (for bills and receipts); In addition, it is best to prepare old towels (soft cotton, which are used to wipe bricks after pasting) and plastic bags (wrapped around the pipeline joints to prevent dirt from blocking) at the construction site in advance.

(2) Choose an auspicious day and start shooting.

Before the workers enter the site, it is best to personally measure all corners of the house, write it down with a pen ruler and mark it clearly. Don't be lazy. The contents of the measurement mainly include:

1. Define the areas involved in the renovation process. Especially tile area, wall paint area, wallpaper area and floor area;

2, clear the bearing wall size. Especially it is necessary to design the wall size of furniture in the future.

It's time to buy radiators.

(3) The main body is removed to make the space more practical.

The main body demolition and reconstruction is the first project, which mainly includes wall demolition, wall building, wall covering, heating demolition, plastic steel window replacement and so on. Remove the garbage in time to ensure the cleanliness of the room, but also for the convenience of construction.

At this point, it's time to set up the product door.

At this time, it is best to browse the cabinets, range hoods, cookers and water heaters and make sure.

(d) Hydropower transformation, and arrange the use of each space.

Hydropower transformation, no regret medicine to eat. Bricks are stuck on the wall and the ceiling is sealed, so it is difficult to add another socket. So be sure to locate the switches, lights, basins, bathtubs, washing machines and so on.

Before the hydropower transformation, the cabinet designer should take measurements at home to help you determine the transformation scheme of power supply and waterway.

Water heater, it is also best to send someone to design the position of power supply and interface according to the model you determine.

Remind you: it is best to leave a power socket on the wall under the basin, which is convenient for loading kitchen treasures.

Air conditioning holes and power supply should be placed on the wall of the bedside as far as possible to avoid air conditioning blowing directly at people in the future.

Keep a distance of 20 cm between the strong and weak points, such as a distance of 20 cm between the socket and the network cable.

(5) Winding the riser and winding the ugly pipe.

Considering the humid environment of kitchen and bathroom, wooden keel must not be used as the material of riser! Everyone must be careful, even if the wooden keel is painted with antirust paint.

Remember, the vertical pipe is made of light steel keel or red brick. Light steel keel saves space, but the most sturdy and easy to use is red brick.

At this time, you need to buy tiles, jointing agents and so on.

Furniture should be set in advance, and the construction period should be kept well, generally at least 15 days.

(6) Tile pasting must first have a solid texture.

Buy a floor drain before sticking bricks.

Note: buy a special washing machine or shower floor drain to deodorize.

After waterproof napping, we are ready to stick bricks.

In addition to the normal precautions for sticking tiles, the tiles are soaked in water and dried in the shade; The broken tiles are reserved for cutting. In short, the width of tiles on the wall should not be less than 10 cm. This often happens when sticking bricks. For example, the wall width is 1 m, the brick is 32*32cm, and the normal pasting method is 3 whole 1. But 32×3=96, the jointing space of 1 cm should be reserved. Finally, the remaining small bricks can only be pasted 3cm wide.

As long as you make it clear to the bricklayer in advance, the width of the brick on the wall should not be less than 10 cm. He can cut bricks on both sides. Let's take a wall just 1 meter wide as an example, and it becomes 2 whole and 2 small. 32×2=64, reserved 1 cm for jointing, and the small bricks on both sides are 17.5cm, so that it looks not only symmetrical on both sides, but also the whole wall will not be narrow there.

At this time, the basin and faucet should be determined, and then the cabinet designer should be invited to visit for the second time.

At the same time, buy paint (ready mixed paint or varnish), wall paint, nitrolacquer, diluted water, etc. , such as wallpaper, must also be set up first.

(7) Oil workers go into battle and wash and brush.

If you don't buy a finished door, let the worker master do it.

Note: Any carpentry work, even if it's just a pass, should follow this step. The big core board sinks to the bottom, and then it is coated with paint. When mixing oil, irresponsible workers are lazy and brush oil directly on the big core board, which is absolutely wrong. Don't believe the story of selling big core boards. It is no problem to brush oil directly on them. Remember, brush the oil directly, and it won't take long for it to crack completely, remember to remember.

Now you don't have to brush mixed oil, but use spray. Workers had better spray white on the inside of the door and the meter box, which is beautiful and not wasteful.

There's nothing to say about painting the wall. Leveling, grinding and rolling must depend on the skill of your oiler.

Need to remind everyone that if you want to paint the wall, you must pay attention to color matching. The adjusted color is lighter than the color card, and it must not be the same as or darker than the color card, otherwise you will regret it. Because when you paint the wall at least twice, some even three times, the color of the upper wall will get darker and darker.

Different people have different views on whether to spray or roll coating. I use roller coating at home, but I have never tried spraying. It is said that the spraying effect is better, but once it is damaged, it becomes extremely difficult to touch up the paint.

(8) Wallpapers and beautiful walls

Wallpaper is much better than wall painting.

After the wall paint is painted, the oil trade union paints nitrocellulose paint where wallpaper needs to be pasted. The paint can be dried thoroughly the next day, and then the master is invited to paste the wallpaper.

Note: Do not open the window for ventilation within 48 hours after the wallpaper is pasted, and let it dry slowly in the shade.

Tell the master that if something gets stuck, you should ask him to help repair it.

At this time, it is time to buy panels, sockets and lamps.

(9) Install the socket panel

The socket panel can be installed in about half a day.

Remind you: 1, it's best to buy a socket with switch function, especially in the kitchen, so that both rice cookers and microwave ovens can be controlled without plugging in the power supply.

2. Although the socket with switch is good, we should pay attention to practicality. According to my observation, all three sockets of the five-hole power supply with switch are flat. Once your electrical appliance needs three round sockets, there will be the depression of using plug-in boards when the sockets are empty. Therefore, multi-purpose sockets must be used, even if it has no switch control!

At this point, you should buy a ceiling for the bathroom and kitchen.

At this time, if you need to install Yuba, please buy it and install it in front of the ceiling.

(10) The ceiling of the kitchen and bathroom should be sealed with the last ugly part.

Install the water heater and Yuba first. After installation, the ceiling edge can better semi-package the water heater, that is, the connection is more beautiful.

Note: 1, it is best to buy aluminum button ceiling, even if it is demolished after many years, it is worth a lot of money to sell waste aluminum. On the other hand, pvc gusset plates look good, but the quality and performance are average, and plastic things are worthless even if they are sold as waste.

2. Buy gusset plates, and ask the price of the whole package. Don't buy gusset plates and corners separately. But the installation fee is extra.

(1 1) Install cabinets, and a beautiful integrated kitchen is born.

The cabinet is a supporting project, and the range hood, cooker and sink should be arranged in advance. It is best to deliver the goods on the same day and install them together with the cabinet.

Tell the cabinet factory in advance that it is very useful to bring the artificial stone countertops cut off from the stoves and sinks and pack a water meter and pipes.

(12) Installation of finished door

The finished door should be installed before the floor, mainly because the installation steps of the door are complicated, such as hinge, door lock, door suction, door frame and so on. , and use a lot of tools. If the floor is installed first, it is difficult to avoid bumping.

(thirteen) the installation of drying racks, curtain rods, lamps, sanitary ware, bathroom hardware.

It is suggested that these projects with scattered ash should be settled one by one before installing the floor.

(14) Installing the floor

The floor must be leveled before installation. Unexpectedly, after the floor was paved, the corridor was very flat and depressed. I had to take it off, pat it flat with instant powder and spread it again.

Prepare a little pepper in advance, don't buy the so-called insecticidal powder brought by the floor workers, just let them spread it along the kicking angle.

Workers must not cut the floor in the house, cut in the corridor and finally clean the corridor.

(15) Installing radiator

At the end of the decoration, it is the easiest to neglect.

It must be made clear in advance that if the seal on the installation sheet is not the manufacturer's seal, it will not be signed.

Pay attention to the installation list (not the purchase list) of radiator. Who is the stamped part? Many of them do this, and the purchase order is stamped with the manufacturer's seal; The single cover is the seal of the installation team. In this way, the so-called "warranty year" is only the radiator itself, but the material is either steel or copper and aluminum, so as long as it can leave the factory, there is almost no quality problem. The most error-prone place is installation! If you agree to seal the installation team, it basically means that you give up the right to pursue the responsibility of the manufacturer. Once the floor is soaked and the home is flooded, the manufacturer absolutely shirks the responsibility and the installation team can't find anyone. The so-called warranty can only be borne by the user himself.

(16) Land reclamation and clearing

The biggest embodiment of cleanliness, I think, is to clean the glass. It is a terrible thing to climb out and clean such a tall building. Secondly, floor waxing, you have to buy your own wax, which is cheap and easy to use, but you must use a clean waxing machine, which is dozens of times faster than manual waxing.

As for the rest, I don't think we need to rely too much on cleanliness. They just scrape around with small blades, which is not smart.

So after cleaning, you'd better do a detailed cleaning yourself. Go to the supermarket to buy a bag of "Wu Jie powder" and some old towels. Wipe old towels with dry five-clean powder, from door to door, from tiles to kicking corners, from one house to another. Don't be lazy. The result will surely make you proud.

(17) Furniture and household appliances enter the site.

A brand-new home, furniture bears the brunt. Bed, mattress, wardrobe, shoe cabinet, sofa, dining table, etc.

Reminder: The following items should be prepared before the furniture enters the market: disposable shoe covers (don't buy poor quality shoes, they will break when you step on them), several boxes of activated carbon, ladders and floor protective film (it is best to bring a wardrobe and a TV cabinet to protect the floor).

If you buy a cloth bed, remind you to see if all the cloth can be taken off. Because I really can't stand the static electricity of chemical fiber, the next day I tried to take off the original cloth and make a set of pure cotton, but I found that the cloth cover was too long and was nailed into the bed box. Workers are lazy, thinking that I won't open condoms for a year or so. I don't know if anyone else has this experience. Anyway, the master came again the next day, and it was quite troublesome to dismantle the dead bed. Send home appliances quickly, and wait until money is tight or not in a hurry. Anyway, electrical appliances are more and more advanced and cheaper.

(18) Accessories and decorations make the home tasteful.

With decorative paintings and beautiful curtains, the gentle taste of home comes out.

Remind you: don't spend too much money on the dressing of curtains. Curtain heads and lead pendants are necessary, but eight ten-dollar lace, cloth buttons and ears cost twenty or thirty dollars more per meter, which is unnecessary and ugly.

The following is divided into "purchase order" and "decoration order" to help you clear your mind.

In fact, "what to buy first, then what to buy" and "what to pack first, then what to pack" are actually completely different concepts. Many products are customized, so it is necessary to reserve the product cycle (such as finished doors, cabinets, etc.). ). And many goods, even if they are not customized, must be determined in size or use mode before the decoration process can serve them more appropriately (such as water heaters, range hoods, cookers, etc.). ). Therefore, it is necessary to clarify not only the decoration order, but also the purchase order.

Purchase order:

(1) Tools (tape measure, calculator, clip)

(2) radiator (change the position and pipeline in advance, and install it at the factory gate after the wall is completed)

(3) finished product door (the production cycle is long, so it should be decided in advance, the foreman should be present when measuring, and communication is better)

(4) Cabinet (there are two door-to-door measurements, and the work of changing water into electricity depends on how the cabinet is designed)

(5) range hoods, cookers, sterilizers, dishwashers, etc. (Look at the model and put it in the cabinet after you buy it)

(6) Water heater (the kitchen treasure should be bought together with the water heater, which is advantageous and convenient)

(7) ceramic tile (the loss of ceramic tile should be fully considered! I'd rather have more, but I can return them in the end.

(8) Furniture (the production cycle is also long, so it should be decided in advance. When you buy the finished product, you should bring the size map of the apartment. If it is customized, please wait until the space is fully planned before measuring)

(9) Sanitary ware and faucet (at least make sure to determine the specific size of the dish basin before measuring the cabinet twice. Please make sure that the sink is in place before installing the cabinet)

(10) paint, wall paint, nitrocellulose paint, etc. After the oil is cleaned, paint the wall or wallpaper.

(1 1) Panel and socket (make sure that the socket is in place before cabinet installation to facilitate electricity use)

(12) lamps (it is best to buy lamps at one time, and the quality of energy-saving bulbs must be better, and Philips is the best).

(13) aluminum gusset plate (used for kitchen and bathroom ceilings, requiring merchants to cover all items to prevent gusset plates and corners from counting money)

(14) Clothes hangers, window rails and bathroom hardware (it is best to install them uniformly before cleaning. Lamps and lanterns, sanitary ware and hardware, clothes hangers, window rails, etc. )

(15) Floor (if the quantity is over-reported, you can choose more than one, but if you pay more, you will get a refund).

(16) Curtains and bedding (after cleaning, pl's home can be decorated with fabric after furniture enters the site).

Decoration order:

(1) main body transformation and demolition

(2) Hydropower transformation

(3) Wrapping the pipeline

(4) Tiling

(5) Woodworking (pass, etc. )

(6) Brush oil

(7) Paint or paste wallpaper on the wall

(8) Install the socket panel

(9) Ceiling in kitchen and bathroom

(10) cupboard

(1 1) Install the finished door.

(12) Installation of lamps, sanitary wares and bathroom hardware

(13) Install clothes hangers and window rails.

(14) floor

(15) radiator

(16) recycling and cleaning

(17) Furniture and household appliances

(18) Curtains and Bedclothes