After the cement lime stabilized soil subbase is completed, how long will it take for the next working procedure to be maintained?
According to the current traffic industry standard JTJ 034-2000 "Technical Specification for Construction of Highway Pavement Base", it is required to maintain health for 7 days.
/kloc-the new standard jtg/tf20-20 1 5 "technical rules for the construction of highway pavement base", which was implemented in August, should be no less than 7 days, and it should be extended to 2 days before the superstructure construction.